Fastsource Limited were employed to conduct the demolition and site clearance works of old flats to facilitate the construction of new dwellings for the Jewish Community in the outskirts of Leeds.

As the project was on a steep hillside, surface water management bunds and basins were installed.

Works consisted of soft strip work, Asbestos Removal, mechanical demolition, & site clearance of all resultant material offsite and the construction of new development Platforms.
20 and 40 yard Ro-Ro skips were utilised for segregated disposal of separate waste types, ferrous and non-ferrous metal, clean timber for biomass, UPVC & general waste for further segregation at nearby MRF sites

Mechanical Demolition was conducted by 1nr 25 Volvo 360 Excavator operated by one of our experienced demolition operative


Various hydraulic attachments were utilised throughout the works to ensure maximum efficiency, Selector Grapple and Concrete Breakers


With a strong emphasis on the reduction of dust nuisance a ‘motofog’ dust suppression unit was in operation throughout the project much to the satisfaction of the site team and neighbours

Slabs and foundations were broken out to remediate the areas for future development

Works areas were segregated so that demolition could progress in isolation to groundworks activities

Fastsource Tippers were utilised to remove the hard material from site to our aggregate recycling facility for production of 6f5 and Type 1

Related Projects